8 Rail North Partnership Operational Update PDF 398 KB
To receive an update on rail operational matters and updates from the operators and Network Rail.
Lead: Gary Bogan
Additional documents:
Minutes:
8.1 In introducing this item, the Chair highlighted the noticeable improvements in both Northern and TPE. He also informed the Committee that Avanti West Coast will address concerns about their performance and their announcement of a reduction to the December timetable between London and Manchester which will impact on the public over the Christmas period.
8.2 Members received an update from Mr Andy Mellors who outlined the Avanti West Coast recovery plan. He explained that the plan has allowed them to build back the timetable from December 2022, including the restoration of the three trains per hour on the Manchester route. He informed the Committee that the plan is working and delivering significant measurable improvements in performance as well as rebuilding the trust and confidence of customers and communities.
He then highlighted some key areas of work which included: improving train crew availability, expediting drivers through training, tackling structural issues in rostering to make sure that resources align to service requirements and reducing reliance on overtime working.
Additionally, he explained that a third of the Avanti driver workforce is over 55 years old and as a result they are recruiting 70 trainee drivers per year over the coming years, already having introduced over 100 new drivers into productivity.
He then highlighted the challenges of the last couple of months in relation to punctuality as a result of infrastructure and weather disruption. He stated that they have been working with Network Rail to address these issues.
He provided the Committee with an explanation as to why they have needed to reduce the timetable between London and Manchester in the run up to Christmas, stating that this is due to residual crew availability issues caused by historic leave agreements that predate the recovery plan. He stated that by working in this way they hope to provide a more reliable service during these weeks. He also informed the Committee that during this period the 11-car Pendolino fleet will be used on the Manchester route. He explained that in order to address the leave issue going forward they are working with employee representatives to get a better spread of leave throughout the year; negotiations are ongoing and it is hoped that revised annual leave rosters can be secured for the start of January 2024.
8.3 The Chair expressed concerns at how Avanti is currently operating and stated that the railway needs to move to be in a different place in 2024. He highlighted the fact that only a quarter of Manchester to London trains arrive on time and whilst understanding that some of the issues are out of Avanti’s control, others are. He was critical of the service being provided for one which is so vital to the economy.
He then enquired as to how many drivers they currently have and how many are needed to ensure that there is not a repeat of the 2023 issues in 2024.
In response Mr Mellors stated that there are over 600 drivers currently on the books ... view the full minutes text for item 8